June 2005 Public meeting and formation of steering group
July 2005 First meeting of the steering group
  Attend Suffolk ACRE's Application Workshop
August 2005 Elect officers to the steering group and form working parties
  Identify stakeholders
  Start budget preparation
September 2005 Plan timetable
  Finalise budget
October 2005 Apply for funding from the panel meeting on 17th October
  Attend Suffolk ACRE's Consultation Workshop
November/December
2005
Carry out an audit of facilities and services
  Carry out needs analysis of residents' views and include -
  consultation of specific target groups e.g. young people, the elderly, the business community
January 2006 Agree content of the questionnaires and other surveying methods
  Identify and approach volunteers for distributing and collecting questionnaires
February 2006 Design questionnaires and run trials
  Train volunteers
March/April 2006 Distribute and collect questionnaires
May/June/July 2006 Collation of data
August/September 2006 Production of report and action plan
October 2006 Presentation of report in the village
  Delivery of full report to partners in the action plan and digest to all households
  Inform local media of our achievement
  Present the Plan to the Parish Council for formal adoption

 


 

Contact

emails addressed to <ideas@melforward.org.uk> will be circulated to all members of the Steering Group.

NB From the point of view of Privacy Protection, personal information (such as names and email addresses) collected for this Parish Plan will not be used for any other purpose, and will not be disclosed to third parties in any form.

 

top of this page

return to MelForward Start page

return to village front page

This page was updated on 11th December 2005

Navigation bar